enter image description here New Glass Shower Door

Week of August 19th

The full crew is back today. Chris, Zack, Ed, Gordie (the electrician) are all doing various things. The shower door has arrived – can’t wait to see it. Then the bathroom is almost done – just grab bar, and towel bar accessories to be added.

The glass door for the shower arrived but when they asked me where I wanted the glass door to sit-- it brought up an issue. They did not have the hinge needed to set the glass where I wanted it, so they’ll have to have it sent overnight and come back Wednesday to finish the install. Always something!

Meanwhile, a lot of the little things are being finished.

The hinge for the shower came on Wednesday and the glass door was installed. It looks great.

Chris and Zack did some final last-minute stuff and the cleaners (a mother and daughter) came on Thursday. The house looks great. We are DONE – on Schedule.

We are starting to bring stuff in from the garage over the weekend.